Item | Project Title | Client | Date of | Contract Amount | |
Commencement | Completion | HK$ | |||
1. | A&A Works at No 23 Soy Street | Bash Engineering Co Ltd | 11/2005 | 12/2005 | 27,500.00 |
2. | A&A Works at No. 3 Cannon Street | Bash Engineering Co Ltd | 12/2005 | 12/2005 | 31,170.00 |
3. | A&A Work at United Christian Hospital (BD 2-3/4078/85(1)/13) | United Christian Hospital | 07/2006 | 12/2006 | 50,000.00 |
4. | A&A Work at G/F & 1/F, No. 8 Russell Street (BD 2-3/3096/97/7) | Emperor Group | 10/2006 | 01/2007 | 758,000.00 |
5. | Site Formation Work at No. 5-19, South Bay Close | Landlord | 06/2007 | 06/2008 | 17,000,000.00 |
6. | A&A Work at G/F, No. 16 Pak Sha Road (BD 2-3/2196/54/3) | Landlord | 12/2007 | 04/2008 | 1,100,000.00 |
7. | A&A Work at G/F & 1/F, 518-520 Nathan Road (BD 2-3/4430/73/5) | Mirror Group | 12/2007 | 06/2008 | 2,810,000.00 |
8. | A&A Work at Unit 1101 Metro Centre I (BD 2-3/4088/89/2) | Landlord | 03/2008 | 04/2008 | 100,000.00 |
9. | A&A Work at Flat 25B & 26B, Pacific View (BD 2-3/3109/87/7) | Landlord | 02/2008 | 07/2008 | 200,000.00 |
10. | A&A Work (Cladding) to Footbridge in TKO (BD 2-3/7199/98(FB)/2) | Sino Group | 01/2008 | 08/2008 | 300,000.00 |
11. | A&A Work at 5D & 6D, Tower 3, the Regalia (BD 2-3/4057/92/2) | Landlord | 11/2008 | In progress | 200,000.00 |
12. | A&A Works at G/F, No. 5 Lan Fong Road (BD 2-3/2153/54/5) | Landlord | 11/2008 | 01/2009 | 1,400,000.00 |
13. | A&A Work at 9-11 Moon Street | Landlord | 03/2009 | In Progress | 1,850,000.00 |